Q1. Which of the following is required by Scrum? (choose the best answer)
A.Sprint Retrospective.
B. Developers must stand up at the Daily Scrum.
C. Sprint Burndown Chart.
D. Release Planning.
E. All of the above.
Correct Answer: A
Q2. Which of the following is an example of an Increment? (choose the best answer)
A.A plan for the overall product release.
B. A mock-up of the product marketing materials.
C. A design for the product.
D. A product roll-out plan.
E. A valuable, useful set of product features.
F. All of the above.
Correct Answer: E
Q3. True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.
A.True
B. False
Correct Answer: B
Q4. How should a Scrum Team deal with non-functional requirements? (choose the best answer)
A.Manage them during the Integration Sprint prior to the Release Sprint.
B. Assign them to the lead developers on the team.
C. Ensure every Increment meets them.
D. Make sure the release department understands these requirements, but it is not the Scrum Team's responsibility.
Correct Answer: C
Q5. Who is accountable for managing the progress of work during a Sprint? (choose the best answer)
A.The Developers.
B. The most junior member of the team.
C. The Scrum Master.
D. The Product Owner.
Correct Answer: A