Q1. For a specific Sprint Backlog item that has been started, what is the best chart (analytic) to determine when it will be finished? (choose the best answer)
A.Throughput Run Chart.
B. Cumulative Flow diagram (CFD).
C. Work Item Aging Chart.
D. Control chart.
Correct Answer: C
Q2. What is Kanban? (choose the best answer)
A.A methodology aimed at visualizing your Workflow for effectiveness and enhance productivity within the team.
B. A strategy for optimizing the flow of value through a process that uses a visual, Work in Progress (WIP) limited pull system.
C. A set of practices that are additive to the Scrum framework.
D. None of the above.
Correct Answer: B
Q3. True or False: Little's Law is used to forecast a Scrum Team's output.
A.True
B. False
Correct Answer: B
Q4. True or False: When the Developers add Kanban to Scrum, the way they use the Sprint Goal during their Daily Scrum changes.
A.True
B. False
Correct Answer: A
Q5. Which of these is NOT a good description of Cycle Time? (choose the best answer)
A.The time a work item takes from initial idea/concept to feedback returned from customers after a production release.
B. The length of time a work item stays in one column.
C. The number of items that move into the delivery/end point per time period (e.g., daily/weekly).
D. The time a work item starts until when it finishes.
Correct Answer: C