Q1. A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?
A.Visit the Project page and create a new filter. Update the 'Pending Approval' filter to 'true' and update the Project Owner ID field to the project manager's name. In the grouping tab, add a grouping for project name.
B. Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the 'Pending Approval' filter to 'true,' and update the Project Owner ID field with the project manager's name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.
C. Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager's name and update the Object ID field to 'tasks' and 'issues.' In the grouping tab, add a grouping for project name.
Correct Answer: B
Q2. What are two characteristics of a Group in Workfront? (Choose two.)
A.A Group can be tagged in an Update thread communication.
B. A Group assignment is not required for a user.
C. A Group can be associated with a Company or a Project.
D. A user can be assigned as Group Administrator of a Group.
Correct Answer: C, D
Q3. What is unique to a Scrum iteration?
A.Backlog of stories and issues
B. Workload Balancer for assigning users to tasks
C. Burndown Chart
Correct Answer: C
Q4. Which group of project elements can be used to monitor an active project's progress?
A.Gantt chart, project Condition, and Metrics
B. Risks, planned hours, and resource utilization
C. Project status, Updates, and Sharing
Correct Answer: A