Q1. The purpose of the Nexus Integration Team is to: (choose the best two answers)
A.Raise transparency.
B. Manage the Nexus.
C. Be accountable that an Integrated Increment is produced.
D. Integrate the work of the Scrum Teams.
Correct Answer: A, C
Q2. Scenario B: Six Team Nexus with complex dependencies A six team Nexus is developing a complex product, with different parts of the product that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams. Some individual Scrum Teams in this Nexus have said that they do not see how the work they are doing is contributing to the product's progress. What is the best remedy for this situation? (choose the best answer)
A.During Nexus Sprint Planning, have all the teams plan the Sprint together in one room, so they can see what other teams are working on.
B. During Nexus Sprint Planning, ensure that all Scrum Teams understand the Nexus Sprint Goal.
C. Ask the Scrum Master to explain to the teams that the Product Owner can choose which features to work on, as she has the final say.
D. During Nexus Sprint Planning, ask each Scrum Team to create a Sprint Goal that describes the purpose of the Sprint.
Correct Answer: B
Q3. A company has five products and are using Scrum for product delivery. Which statements represent the best option for how Product Ownership might be structured? (choose the best two answers)
A.Assign as many Product Owners as needed to communicate expectations and requirements to the Scrum Team.
B. One Product Owner responsible for each product. Each of these Product Owners may delegate work as needed, but they remain accountable for the value delivered by their product.
C. One Product Owner responsible for all five products. This Product Owner may delegate work as needed, but the Product Owner remains accountable for the value delivered.
D. One primary Product Owner and one Product Owner for each product. The primary Product owner delegates all accountability for delivering value to the Product Owners for each product.
Correct Answer: B, C
Q4. Scenario C: Dependencies and Product Backlog items During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams identify many dependencies. This makes it hard for them to choose the work they could pull into their individual teams for the next Sprint. No matter how they reorganize the Product Backlog items, they continually find more or new dependencies. What would you recommend to the two teams that are continually dependent on each other to help them manage their work? (choose the best answer)
A.The Nexus Integration Team should be responsible for integrating the work of these two Scrum Teams.
B. Reorganize these two Scrum Teams so that one is responsible for development and one is responsible for integration.
C. Merge the two Scrum Teams together.
D. Ensure the appropriate representatives from both teams are present during Cross- Team Refinement.
Correct Answer: D