Q1. A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?
A.IaaS
B. XaaS
C. DaaS
D. SaaS
Correct Answer: A
Q2. Which of the following is a characteristic that defines a project?
A.Will produce a profit
B. Uses outside resources
C. Requires a well-defined scope
D. Has a defined start and finish
Correct Answer: D
Q3. A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
A.Each feature will have a different owner.
B. The majority of the team can only meet on a weekly basis.
C. The stakeholders have provided a specific deadline to meet.
D. Each feature has a specific budget allocation.
Correct Answer: C
Q4. Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
A.Sprint retrospective
B. Sprint review
C. Sprint planning
D. Daily Scrum
Correct Answer: B